County Materials Meets WisDOT’s Expedited Bridge Construction Schedule

County Materials Meets WisDOT’s Expedited Bridge Construction Schedule

Location:

Osseo, WI

The Wisconsin Department of Transportation (WisDOT) successfully met the expedited schedule for the replacement of two bridge structures on I-94 over County NN, north of Osseo, WI. Consistently heavy traffic along the interstate required accelerated construction to minimize lane closures and the impact on traffic. Two County Materials prestress concrete girder manufacturing facilities contributed to meeting the challenges of this project.

To meet the fast-paced demand of this project, County Materials simultaneously produced girders for the bridges at two different facilities. County Materials produced eight girders in Roberts, WI, then delivered the bridge components south to the site; the company produced another eight girders in Janesville, WI, which were transported north, along I-94.

The eight beams delivered from Roberts, WI, had to turn around on U.S. Highway 10 and I-94 to stage in the right place. The large size of the girders meant that trucks were unable to maneuver the turn back on the highway. Instead, County Materials’ experienced drivers had to back down the I-94 west off-ramp, then make a y-turn to proceed to the staging area. County Materials’ dispatch team coordinated with the installation crew onsite to get the delivery times set to their needs, and also worked with the Wisconsin State Highway Patrol to briefly close the exit for maneuvering the girders. 

The first structure delivered was produced in Janesville and delivered on August 27th, 2019. The Janesville facility produced eight, 72W style beams that were 129 feet long and weighed 130,000 pounds each. The second group of girders was produced in Roberts and delivered on September 11th, 2019. This group also included eight 72W style beams, that measured 145 feet long and weighed 146,000 pounds each.

Catalog Request